Scheduling

How to set up recurring visits

Book daily, weekly, monthly or yearly visits on a job in one go, bill each visit automatically if you want, and move or stop the series later.

Updated By Adrian Gluchowski5 min read

On this page

Repeat work lives on a job. Open the job, press Schedule a visit, and pick how often under Repeats. Chalk books the whole run of visits on the calendar at once, at the same time of day, with the same crew. You need the Book and move visits permission.

Book a repeating series

  1. Open the job. Jobs come from approved quotes: see Turn an approved quote into a job.
  2. Press Schedule a visit, either the main button at the top of the job or the one on the Visits card.
  3. Pick the date, the Starts and Ends times, and Who's going?.
  4. Under Repeats, pick how often.
  5. Under For how long?, pick when it stops.
  6. Press Schedule.

If the job was waiting with a visit that has no time yet (a job made from a quote starts with one), the series starts from that visit, so nothing is left behind on the waiting list.

The options under Repeats are:

  • Just this once (a single visit)
  • Every day
  • Every weekday (Monday to Friday)
  • Every week
  • Every 2 weeks
  • Every month
  • Every 3 months
  • Every 6 months
  • Every year

The options under For how long? are:

  • A set number of visits, from 2 to 60.
  • Until a date.
  • Keep going, which books the next 60. Cancel the rest of the series when the work ends.

Every day and Every weekday are for one job that runs day after day, like a kitchen or a three-day stain. Chalk treats that run as one piece of work: see Jobs that take more than one day.

Before saving, Chalk checks every visit in the run against the crew's other bookings and time off. If any clash, it tells you which days and lets you book it anyway. A monthly visit set for the 31st lands on the last day of shorter months.

Afterwards the job page says the work repeats, how many visits are done out of the total, and when the next one is. The jobs list marks it repeats.

Bill each visit

When you pick a repeat, the form also shows Invoicing for each visit. It applies when a visit is marked complete:

  • No automatic invoice (the starting choice). Bill the job however you usually do.
  • Draft an invoice, I will send it. Each time a visit is marked done, Chalk makes a one-line invoice for the amount you enter per visit, and leaves it for you to check and send.
  • Send the invoice to the customer. The same invoice, sent to the customer when the visit is done, by text or else by email. It stays a draft for you to send if the customer has no phone or email on file, if neither texting nor email is set up, or while automations are paused.

A visit is never billed twice. The job's own final invoice is separate, so leave this off for fixed-price work you bill once.

Move or change visits in a series

Drag a visit in a series to a new time and Chalk asks This visit repeats:

  • Just this one moves only that visit.
  • This and all future moves that visit and every later visit that is not done yet by the same amount. If you dropped it on another person's column, they take over those visits too.
  • Never mind leaves everything where it was.

Visits already done, and visits waiting with no time, are not moved.

For a run booked Every day or Every weekday, the question is This visit is one day of a run, and the button reads This and the later days. On an Every weekday run the later days move by working days and skip the weekend: move Thursday's visit to Friday, and Friday's goes to Monday.

Change the time or crew from the visit (the Change buttons next to When and Crew) to change that one visit only.

Rain day moves only the rained-out visit of a series. The rest of the series stays put. See Reschedule a whole day for rain.

Stop a series

  1. Open any visit in the series and press Cancel remaining visits, or use the same button in the job's More menu.
  2. Confirm. Every visit on the job that is not done yet is cancelled. Completed visits stay.
  3. Made a mistake? Press Undo on the message that shows straight after.

To cancel only one visit, open it and press Cancel this visit.

Good to know

Be clear on these before you sell a maintenance plan (the plan itself is covered in maintenance plans for service businesses):

  • Only the nine patterns above. You cannot pick your own weekdays, and there is no "every other month" or "second Tuesday of the month".
  • No changing the pattern later. To go from every week to every 2 weeks, cancel the remaining visits and book a new series.
  • At most 60 visits per series, booked up front. Chalk does not add more later on its own. When a Keep going series runs low, book another run.
  • No holiday skipping. Only the first date is checked against the days your shop is closed. Move or cancel visits that land on a holiday.
  • No repeating invoice on its own. Per-visit billing belongs to a job with visits. There is no stand-alone invoice that repeats every month.
  • No Repeats on the calendar. A visit booked by clicking the calendar is always a single visit. Start a series from the job.
  • Each visit in a weekly, monthly or yearly series gets its own day-before reminder. On an Every day or Every weekday run, the customer is reminded before the first day rather than every evening, as long as the days have not been moved and Skip if they already heard from you that day is on. Crew see each visit on their Today screen like any other stop.
  • Work that comes back every year or two, rather than on a fixed series, is repeat work.