Seasons and planning

Busy season prep: a checklist for service contractors

Get ready for the spring rush: prices and quotes, crew and training, equipment, lead handling, scheduling rules and cash, in one checklist for February.

Adrian GluchowskiOwner of Superior Stain Solutions, builder of ChalkLast reviewed 7 min read

On this page

Spring does not arrive slowly. One week the phone is quiet, and the next you have forty messages, a crew that has not worked since November and a sprayer that will not prime. The shops that handle it well did the boring work in January and February.

This checklist is built to be done in the six weeks before your first big week. Each section has what to do, who does it, and when. If your season starts in March, start in late January. If it starts in May, start in March. The section on the full year is the exterior contractor calendar.

Six weeks out: prices, quotes and templates

Do this first, because every lead you get will touch it.

  1. Look at last season by job type. Which jobs made money, and which did not? See job costing for contractors.
  2. Set this year's prices. If your costs went up, your prices should too. Give repeat customers 30 days' notice. See how to raise your prices.
  3. Update your price list with this year's prices for materials and labor.
  4. Refresh your quote templates: the scope, the terms, the weather clause, the deposit and your exclusions. Read them as a customer would.
  5. Set your deposit rule. A deposit holds the date and funds the materials. See deposits for contractors.
  6. Decide your minimum job size and your travel zone. In a rush, small and far jobs cost the most.
  7. Write the early-booking offer's end date and stick to it.

Owner: you. Done by: week 6.

Crew: hire, train, set pay

A season goes wrong when the crew is not ready on day one.

  1. Count the people you need. Use the capacity math below, not a guess.
  2. Start hiring early. Good people have jobs by March. See hiring seasonal crew.
  3. Settle pay before the first shift. Day rate, hourly or a share, written down. See day rate vs hourly crew pay.
  4. Hold a training day before the first customer. Run the job on your own shop, a friend's fence or a practice panel. Show the steps, the photos you want and how to talk to a homeowner.
  5. Train on safety. OSHA's fall prevention campaign says falls are the leading cause of death in construction (389 of 1,034 construction deaths in 2024). It tells employers to plan each job's safety needs, provide the right ladders and gear for work six feet or more above the ground, and train every worker. See OSHA fall prevention.
  6. Check who is returning, and send each their start date in writing.
  7. Set clock-in rules and who covers when someone is out.

Owner: you or your lead. Done by: week 3.

Capacity: how many jobs can you do?

Do the math before you promise dates.

4 people x 40 hours                         = 160 person-hours a week
Billable share (drive, setup, breaks: 70%)  = 112
Weather: lose 1 day in 5 (20%)              = 112 x 0.80 = about 90
Average job: 18 person-hours                = 90 / 18 = 5 jobs a week

Replace the numbers with yours. Your own records tell you the average hours per job. If you expect 12 estimates a week in April and win 40%, that is about 5 jobs a week, and you are at capacity. If you expect more, you need another crew, a longer wait or a higher price.

Equipment and the truck

Do not find out in the first week that the pump is dead.

  • Test and service every machine: pressure washers, sprayers, mowers, trimmers, blowers, vacuums. Run them for an hour.
  • Stock the wear items: nozzles, O-rings, hoses and fittings, pump oil, filters, blades, trimmer line, spray tips.
  • Inspect ladders, scaffolds and harnesses. Replace anything damaged.
  • Service the truck and trailer: oil, tires, brakes, lights, hitch.
  • Replace PPE: gloves, respirators, eye protection, boots.
  • Check inventory of materials and supplies. Order what has a long lead time. Buy ahead only if cash allows.
  • Check your insurance certificate and the dates on your licenses.

Owner: you, with a lead. Done by: week 2.

Lead handling: replies, booking page, follow-ups

Spring is when leads pile up and some go cold. Set this up before it starts.

  1. Decide who answers and by when. Answer the same day. At the least, send a text that says you got it and when you will call back.
  2. Set the greeting on your phone and your auto-reply to say how fast you respond and how to book.
  3. Put a request form or booking page on your website, social pages and truck. It collects the address, what they need and photos, even when you are on a ladder.
  4. Write your first reply and your quote texts now. See text message templates.
  5. Set a follow-up rhythm for quotes that nobody answers: 3, 7 and 14 days is a common pattern. See how to follow up on estimates.
  6. Estimate fast. Photo or video estimates cut drive time. See should contractors charge for estimates.

Owner: whoever answers the phone. Done by: week 2.

How fast you answer matters more in April than in any other month. See speed to lead.

Scheduling rules and weather buffers

Rain will cost you days. Decide now how you will handle it.

  • Build slack into every week and say it on the quote. See rain delays and a weather policy.
  • Set your go or no-go rules from the data sheets: minimum temperature, dew point, dry times. See weather rules.
  • Decide who moves first when a day is lost, and how customers are told.
  • Set how many jobs a crew does per day and how far you will drive.
  • Block time off for you and your crew now, before the calendar fills.

Owner: you. Done by: week 2.

Cash for the ramp-up

Spring costs money before it makes money. In the example in cash flow for seasonal contractors, the lowest balance is in April, not January.

  1. Make your forecast for the next 12 months. An hour is enough.
  2. Check your reserve against the lowest point.
  3. Take deposits on every big job so materials are paid for.
  4. Line up credit before you need it, if you use it.
  5. Know your tax payment dates, April 15 and June 15 among them.
  6. Plan the first payroll and the first week of materials.

Owner: you. Done by: week 4.

Your own limits

The one person who cannot be replaced in a rush is you.

  • Decide your hours. Estimates at night are what burn people out. Pick two evenings a week at most, and a time you stop.
  • Decide what you will hand off in season: scheduling, invoices, reminders, the first reply to a lead.
  • Plan one day off a week, and put it on the calendar.
  • Tell your family the dates you will be hard to reach.
  • Say no sometimes. A full calendar with a long wait is better than a promise you cannot keep.

The checklist

Six weeks out

  • Review last season by job type
  • Set prices and the customer notice
  • Update the price list and quote templates
  • Set deposit and minimum job size
  • Set the early-booking offer's end date

Four weeks out

  • Count the crew you need (capacity math)
  • Start or finish hiring; settle pay in writing
  • Build the 12-month cash forecast
  • Check the reserve and credit

Two weeks out

  • Service and test all equipment; stock the wear items
  • Inspect ladders and gear; replace PPE
  • Check insurance certificates and licenses
  • Put up the request form or booking page
  • Write first reply and follow-up texts
  • Write the weather rules and the customer wording

One week out

  • Hold the training day and safety talk
  • Confirm each person's start date
  • Block your days off
  • Check the first two weeks of the schedule

How Chalk helps

This part is about our software. Skip it if you only want the checklist.

  • Automations. Only the day-before visit reminder and On my way are on at the start. Everything else, such as quote follow-ups, invoice reminders and review requests, is off until you add it and turn it on under Settings > Automations. See automations.
  • Your price list. Update it under Settings > Price book. Quotes you already made keep their old prices. See set up your price book.
  • Your booking page and request form. Set them under Settings > Website. Every one sent in lands on your Funnel as a new lead. The request form is always on, and online booking is off until you turn it on. See online booking and a request form.
  • Seasonal crew. Invite people under Settings > Team. Each person after the owner needs a seat at $14 a month, and you can remove a seat later. See add your team.
  • Rain. Rain day moves every work visit on a rained-out day in one go. See how to reschedule a whole day for rain.
  • Deposits and timed offers. See take a deposit and optional extras, timed offers and quote expiry.

Sources

  • OSHA, Fall prevention campaign: falls as the leading cause of construction deaths, using 2024 Bureau of Labor Statistics data
  • The capacity example and the follow-up rhythm are illustrative arithmetic and common practice. Use your own numbers.
  • The timing (six weeks out) is a suggestion, not a rule.